Standing Building Committee approves Water Treatment Plant delay monitoring and $54K mitigation payment.
Standing Building Committee votes on Water Treatment Plant delays and $54K settlement. Vice-Chair Matt Baldassari presided as the committee unanimously voted to require the Department of Conservation to submit its start-up and testing plan to the owner's project manager, Sharon Water Department,
Sharon Standing Building Committee · Meeting of June 23, 2026
SHARON — Standing Building Committee votes on Water Treatment Plant delays and $54K settlement. Vice-Chair Matt Baldassari presided as the committee unanimously voted to require the Department of Conservation to submit its start-up and testing plan to the owner's project manager, Sharon Water Department, and project designer by July 7, 2026, citing a 45-day slip in substantial completion and potential liquidated damages of $4,300 per day. In a separate action, the committee voted 4-3 to approve Invoice Voucher #42 for $54,000 to finalize the Tavares Family Mitigation agreement.
Members expressed frustration that the Department of Conservation had not shared schedule details or formal testing plans despite repeated requests spanning several weeks.
In the full story:
- The complete report — 357 words
Source: the Sharon Standing Building Committee meeting of June 23, 2026, compiled from the official minutes.
Members read the rest of this story and every Sharon meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Sharon who follows town government? Share Townbrief Sharon: they can sign up free.