Sharon Standing Building Committee approves Water Treatment Plant invoice, appoints committee member.
Sharon Standing Building Committee approves $223,208 invoice for Water Treatment Plant construction. The committee unanimously backed the payment covering work completed January 1-31, 2026, after review by APEX, Weston and Sampson, and member Roger Thibault. James Campisano was unanimously
Sharon Standing Building Committee · Meeting of March 3, 2026
Sharon Standing Building Committee approves $223,208 invoice for Water Treatment Plant construction. The committee unanimously backed the payment covering work completed January 1-31, 2026, after review by APEX, Weston and Sampson, and member Roger Thibault. James Campisano was unanimously appointed to the Change Order Subcommittee replacing Mike B.
Martin. The WTP project is 50 percent complete with building enclosure expected by May and final completion targeted for year-end 2026. A proposal to add handicapped-operated buttons to library bathroom and children's room doors, estimated at roughly $24,000 total, was tabled pending comprehensive quotes and further technical review.
In the full story:
- The complete report — 364 words
Source: the Sharon Standing Building Committee meeting of March 3, 2026, compiled from the official minutes.
Members read the rest of this story and every Sharon meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Sharon who follows town government? Share Townbrief Sharon: they can sign up free.